Construction progress of new Building in Images
Eine Ebene höherWatch the progress of the construction activities of our new building in Kaiserslautern! We publish photos regularly here.
- 13.06.08 Transformer Station
- The fine layer was superimposed onto the concrete floor and the transformer station for power supply was set up.
- 30.05.08 Production
- The floor pavement is inserted in the production wing and the corresponding offices.
- 30.04.08 Admin. Wing
- The floor heating is installed and the floor pavement is inserted.
- 25.04.08 Facade
- The facade is under construction.
- 18.04.08 Production
- The floor of the production wing is concreted.
- 15.04.08 Interior Fittings
- The interior fittings are continued: the first cables and tubes are installed.
- 03.04.08 Interior Fittings
- Start of interior fittings and mounting of windows.
- 19.03.08 Production
- The roof of the production wing is being completed, the exterior walls are already set up completely.
- 06.03.08 Exterior Walls
- The first exterior walls are under construction. The construction of the roof is continued.
- 25.02.08 Roof
- The roof of the production wing is under construction.
- 12.02.08 Production
- The floor joists and pillars in the production wing are set up. In the administration wing the floor is concreted on both levels. All staircases in the building are concreted as well.
- 29.01.08 Ceiling
- The upper floor is under construction meanwhile.
- 17.01.08 Staircases
- The staircases are identifiable already, ceiling will be one of the next workings
- 18.12.07 Admin. Wing
- Mid of december more and more details of the administrative wing of the new PFAFF building come to the fore.
- 11.12.07 Columns
- The new building takes shape. By december 11th more than 20 columns have been erected.
- 26.11.07 Excavations
- Excavators started with their work in the industrial area end of November.
- 14.11.07 Container
- The general contractor WOLFF & MUELLER installed containers in preparation for earth moving in november.
- 12.10.07 Ground-breaking Cerem.
- A milestone for PFAFF was celebrated with the symbolic ground-breaking ceremony for the new building in the industrial zone, north of Kaiserslautern.
- 31.05.07 Construction Sign
- The construction sign for the new works of PFAFF Industrie Maschinen AG was set up end of may in the industrial area.
- 28.02.07 Building Permission
- PFAFF submitted the application for a building permission for the new building in Kaiserslautern.